House elevation

House elevation process and timeline

What happens, in what order, and roughly how long each stage takes.

Short answerA typical elevation runs through survey and design, permits, preparation, the lift, the new foundation, reconnection and final inspection with a new elevation certificate. Time out of the home is often 2 to 4 months; the paperwork before it can take longer, especially for grant-funded projects.

Stage by stage

StageWhat happensTypical time
1. Site visit and surveyWe assess the house, lot and access. A surveyor confirms existing elevations.1 to 3 weeks
2. Engineering and designStructural engineer designs the lift and the new foundation to the required flood elevation.2 to 6 weeks
3. Fixed price and contractWritten scope and 1 price, including stairs, utilities and access.1 week
4. PermitsBuilding and floodplain permits from your city or county.Varies by city
5. PreparationMove-out, utilities disconnected, site cleared, trenches dug.1 to 2 weeks
6. LiftBeams set and the house raised to height on cribbing.A few days
7. New foundationPiers or columns built, cured and inspected.3 to 6 weeks
8. Set down and reconnectHouse set and anchored, utilities reconnected, stairs built.3 to 6 weeks
9. Final inspectionFinal inspections and a new elevation certificate.1 to 2 weeks

These are typical ranges, not promises. Your schedule is written into your contract.

The elevation certificate

An elevation certificate records how high your lowest floor is compared with the flood level. Insurers use it to price flood insurance and permit offices use it to confirm compliance. A surveyor completes one before and after the work.

Living arrangements

You will need to move out from preparation until the utilities are reconnected and the house passes inspection. Grant programs and flood insurance sometimes help with temporary housing; check the rules of your program.

Questions we get asked

How long does a house elevation take?

Construction is often 2 to 4 months. Engineering, permits and any grant paperwork before construction can take several months more.

Who gets the permits?

We prepare and submit the permit applications with the engineer's drawings and handle inspections.

When can I move back in?

Once utilities are reconnected, stairs are built and the final inspection passes.

Free estimate

Tell us about your project

Sam or the team will call you back within 1 business day to talk it through and book a site visit.

281-326-9719

[email protected]

Request your free estimate

About 2 minutes. Pick a time in our calendar at the end.

$1,000 off your project when you book through our estimate page.*

*Valid on signed contracts of $15,000 or more. 1 per household. Cannot be combined with other offers. Book by December 31, 2026.

☎ CallFree Estimate